During normal operation of a electric vibro hammer pile hammer, the operator must adjust the engine power supply based on the piston's jump height to increase or decrease power. The optimal piston jump height is generally around 2.2 meters. 

The control rope on the power lever is only used during emergency stops and is not generally used during normal operation. 

The power supply of a electric vibratory hammer is adjusted not only based on the piston's jump height but also on power consumption. Low battery voltage may mean that the battery is not being fully utilized; excessive charging cycles may cause battery capacity to decrease, affecting full power utilization; and overloading the motor may cause rapid power consumption or underutilization. The motor's operating status can be monitored by checking the current and voltage meters to ensure operation within reasonable ranges. 

During operation, the operator should frequently check the battery, voltage, and current.

What Should I Pay Attention To When Using An Electric Vibratory Pile Hammer?

This site uses cookies

We use cookies to collect information about how you use this site. We use this information to make the website work as well as possible and improve our services.